Turnkey Power Solution for Telecommunications Centre in Brentford
Enrogen successfully completed a full turnkey project for a telecommunications centre in Brentford, overseeing the design, supply, installation, and commissioning of a custom diesel generator solution. The project featured:
2 x 2,500kVA generators (n+1 configuration) powered by MTU 20v 4000 engines coupled to Leroy alternators.
A 72-hour fuel system to ensure extended power availability.
Acoustic enclosures rated at 75dBA at 1 meter to minimize noise impact.
Advanced Set-to-Set and Set-to-Mains synchronisation controls.
A ComAp control system for seamless management.
The solution also integrated a ComAp system to monitor and control the LV switchgear, transformers, UPS, and generators, ensuring comprehensive operational oversight.